Islamabad: Ahsan Iqbal Highlights Delays and Cost Escalation in Diamer Basha Dam Project

 

Islamabad: Ahsan Iqbal Highlights Delays and Cost Escalation in Diamer Basha Dam Project

Islamabad, September 13, 2024– Federal Minister for Planning, Development and Special Initiatives, Ahsan Iqbal, chaired a review meeting on the progress of the Diamer Basha Dam project. The meeting was attended by the Secretary Planning, Chairman WAPDA, and senior officials of other relevant departments.

During the meeting, Ahsan Iqbal said that the Diamer Basha Dam is a crucial project for Pakistan's water and food security and must be completed expeditiously in the national interest. He said that until 2018, the estimated construction cost of the Diamer Basha Dam was Rs. 479 billion, and Rs. 120 billion had already been spent on land acquisition. However, due to delays and unnecessary postponements during the previous government, the cost of the project has increased significantly. He said that in 2020, construction was hastily started without proper financing, which further compounded the problems.

The Planning Minister said that during the tenure of the previous government, the cost of the project was estimated at Rs. 600 billion and even Rs. 750 billion in various meetings of the standing committees, while on paper, an estimate of Rs. 480 billion was being shown till date. Ahsan Iqbal maintained that the responsibility for the increase in the project cost lies with the previous incompetent government, and due to lack of funding and delays, the cost has now increased from Rs. 479 billion to Rs. 1400 billion.

Expressing regret, Ahsan Iqbal said that even today, a complete financing plan for the project is not available. He suggested that the dam and power projects be separated and the financing of the power project be obtained from private sector.

He further said that even after six years, the revised PC-1 of the project has not been prepared. I had proposed in a standing committee meeting during the previous tenure that work on a project whose PC-1 is more than two years old should not be started.

On this occasion, he also said that in the future, projects will be completed under the Public-Private Partnership to avoid delays in funding and completion. The Diamer Basha Dam will provide a storage of 6.4 million acre-feet of water, which is important for the country's agriculture and industry.

During the meeting, Ahsan Iqbal emphasized that engineering and hydrology students from Pakistani universities should be involved in the construction of the dam so that they can benefit from this national project. Furthermore, the Federal Minister directed all relevant departments to prioritize the completion of the Diamer Basha Dam project and avoid further delays to ensure Pakistan's water and food security.
The Pakistan times
Pakistan Times
Federal Minister for Planning, Development and Special Initiatives, Ahsan Iqbal, chaired a review meeting on the progress of the Diamer Basha Dam project. The meeting was attended by the Secretary Planning, Chairman WAPDA, and senior officials of other relevant departments.

During the meeting, Ahsan Iqbal said that the Diamer Basha Dam is a crucial project for Pakistan’s water and food security and must be completed expeditiously in the national interest. He said that until 2018, the estimated construction cost of the Diamer Basha Dam was Rs. 479 billion, and Rs. 120 billion had already been spent on land acquisition. However, due to delays and unnecessary postponements during the previous government, the cost of the project has increased significantly. He said that in 2020, construction was hastily started without proper financing, which further compounded the problems.

The Planning Minister said that during the tenure of the previous government, the cost of the project was estimated at Rs. 600 billion and even Rs. 750 billion in various meetings of the standing committees, while on paper, an estimate of Rs. 480 billion was being shown till date. Ahsan Iqbal maintained that the responsibility for the increase in the project cost lies with the previous incompetent government, and due to lack of funding and delays, the cost has now increased from Rs. 479 billion to Rs. 1400 billion.

Expressing regret, Ahsan Iqbal said that even today, a complete financing plan for the project is not available. He suggested that the dam and power projects be separated and the financing of the power project be obtained from private sector.

He further said that even after six years, the revised PC-1 of the project has not been prepared. I had proposed in a standing committee meeting during the previous tenure that work on a project whose PC-1 is more than two years old should not be started.

On this occasion, he also said that in the future, projects will be completed under the Public-Private Partnership to avoid delays in funding and completion. The Diamer Basha Dam will provide a storage of 6.4 million acre-feet of water, which is important for the country’s agriculture and industry.

During the meeting, Ahsan Iqbal emphasized that engineering and hydrology students from Pakistani universities should be involved in the construction of the dam so that they can benefit from this national project. Furthermore, the Federal Minister directed all relevant departments to prioritize the completion of the Diamer Basha Dam project and avoid further delays to ensure Pakistan’s water and food security.